Home  

History   

Architecture  

Visit Us   

About Venoge  

Friends of Venoge

Events 

    Putting By, fall 2011

    Open House, 2011 

Restoration 2010  

200th Anniversary     

Workshop 2008   

Workshop Photos  

Efroymson Grant

La Gazette Helvetique

 Links  

 

      

Venoge Restoration

 

 Phase two, 2010

 

     This house is one of the few remaining examples of the French colonial architecture that once characterized the first settlement of Switzerland County. Once common throughout the Mississippi Valley, the house was built ca. 1805-15 on property bought and developed by Swiss native, Louis Gex Oboussier in 1805.
 

 

Our restoration work this year began in  March and is continuing through October. Bringing the house from a nearly bare framework to a building that is livable in the early 19th century manner took many hours of work and asking the right questions of the right people.  The house itself held many answers to questions we asked...but not until we had taken it further back to a skeleton form were some of the answers known.

The frame of Venoge as it stood in March, 2010

Venoge from the west, September, 2010

From the east

The foundation over time had lost some of its continuity and so stones were laid to fill the gaps.  The failed chimney footer was removed and replaced with a poured reinforced concrete one.  The stone removed from the original footer will be reused in a  workspace pavement around the house. A concrete footer was poured to form a pad on which to support the center of the floor joists.

Relaying foundation stones where necessary

Original chimney footer before removal and replacement. Under soil is loosly stacked local limestone.

Preparing the new footer foundation

Beginning to pour the footer

Footer pad poured

Footer poured and chimney breast repaired

Traditional lime mortar was used in building the fireplace. Concrete block was used and will be concealed by plaster.

Beginng to build the firebox.

Building the firebox

Putting in the flue liner

Laying the top of the chimney from scaffolding

Raking the brick joints

Completed firebox

The support for the hearth was found, it was done differently than most: the hearth brick was laid on stone and the wood ledge.  We were able to determine the hearth size by the existing opening.

Shape of trim board around hearth and brick ledge

Starting to lay the brick hearth.

Hearth complete with mantel leaning in place. Pintels were laid up with the brick for the crane.

The remaining original siding was found under the front porch ceiling and concealed under the rear kitchen addition.  There is a bead on the lowest board in the front.  All new siding was run in poplar 1/2 " x 8" as was the original.

Original siding shows under the porch roof.

All siding was painted first with a mixture of lindseed oil and turpentine

Trying out a whitewash mixture

 
The original siding was poplar 1/2 inch thick.  Two sections remained and were found hidden under the kitchen addition and under the front porch ceiling.  Our siding was the same dimensions and species.

Starting the south side siding.

Triming the siding to fit the roof angles

Strenthening the collar ties and gable end framing.

East side nearly complete

 

The original location of the stair to the second floor was a question from the beginning.  The stair that was in place when Venoge was acquired had been put in front of a window and a large beam had been removed to do so. That stair was of a much later date. 

It is not unusual for stairs to be exterior on houses of this type.  A short wall of nogging in the front wall was a puzzle and when a row of nails was discovered in the flooring going to the fireplace wall plus the discovery (when second floor boards had been taken up) of a notch for the stair rail, the answer became apparent.  Measurements were taken which led to the placement of the stair beginning on the porch or what the French call the gallery.

Level follows a row of nails where stairway wall was toenailed

Notch where base of stair post was attached. Empty mortise seen top center...rail was attached here

Empty mortise... tenon of second floor rail attached here.

Installing the stringers for the stairway

Inastalling the poplar risers

Partially finished stairway and tongue and groove cupboard panel wall

Framing the stairway opening

Board and batten doors, beaded and tongue and grooved installed to replicate original doors.

 

Interior view of the west wall.  We were fortunate to have found the original mantel used as a shelf in an outbuilding. 

It is believed that the understair cupboard door is back in its original location. It's second use was in the cupboard under the second stair.

View of the west wall

 
After the floor was leveled the ceiling was jacked up 3.5 inches.  The 24 foot long beams above were strengthened by sistering steel and bolting every twelve inches.  The beam that had been partially removed for the later stair was repaired with a half lap.  A single layer of poplar flooring was installed on the second floor.  The original had been two layers of 3/4 and 1/2 inch poplar with all horizontal joints staggered.

The sagging ceiling was raised 3.5 inches.

Sistering steel to the ceiling beams

Steel in place.

Poplar flooring laid on beams